Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel chromium plating grade 1 as per IS: 1068 and fixing with necessary screws etc., complete

Overall width 35 mm
Item number
9.61.1
Analysis basis
1 meter
Priced inputs
5
Derived rate
₹336.45/ METER
D-01/RATE ANALYSISITEM 9.61.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.61.1 (Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel chromium plating grade 1 as per IS: 1068 and fixing with necessary screws etc., complete Overall width 35 mm) is derived from 5 priced inputs for 1 meter and works out to ₹336.45 per meter after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.61.1DETAILS OF COST FOR 1 METER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0656MATNickel plated mild steel piono hinges 1 mm thick 35 mm wideNickel plated mild steel piano hinges 1 mm thick 35 mm widemetre142.0042.00
0686MATOxidised mild steel screws 20 mm100 Nos0.333.009.90
9977MATCarriage of materialsL.S.1.822.274.13
0112LABCarpenter 2nd classday0.14816.00114.24
0114LABBeldarday0.09736.0066.24
BUILD-UP TO RATE
TOTAL
236.51
Add 1 % Water charges on “W”
+2.37
TOTAL
238.88
Add GST on “X” (multiplying factor 0.2127)
+50.81
TOTAL
289.69
Add 15% CPOH on “Y”
+43.45
TOTAL
333.14
Add Cess @ 1% on “Z”
+3.33
Cost for 1 metre
336.47
SAY
₹336.45
D-02/SOURCEPRINTED PAGE 520
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
520

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 520. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.