Providing and fixing wire gauge laminated veneer lumber shutters conforming to IS : 14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm as per IS :1568, for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, as per directions of Engineer-in-charge: (Note:- Butt hinges and necessary screws shall be paid separately)
- Item number
- 9.31.1
- Analysis basis
- Details of cost of one shutter
- Priced inputs
- 5
- Derived rate
- ₹3,066.20/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.31.1 (Providing and fixing wire gauge laminated veneer lumber shutters conforming to IS : 14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm as per IS :1568, for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, as per directions of Engineer-in-charge: (Note:- Butt hinges and necessary screws shall be paid separately) 35 mm thick shutters) is derived from 5 priced inputs and works out to ₹3,066.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 220x108cm = 2.38sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7154 | MAT | Factory made 35 mm thick shutters with laminated veneer lumber styles rails as per TADS IS:1995 and panels of galvanised wire gauge with average width of aperture 1.4 mm on both directions with wire of dia 0.63 mmFactory made 35 mm thick shutters with laminated veneer lumber styles & rails as per TADS 15:1995 and panels of galvanised wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm | sqm | 2.38 | 1,720.00 | 4,093.60 |
| 9977 | MAT | Carriage of shutters | L.S. | 29.64 | 2.27 | 67.28 |
| 0156 | LAB | Carpenter (average) | day | 0.52 | 857.00 | 445.64 |
| 0114 | LAB | Beldar | day | 0.6 | 736.00 | 441.60 |
| 9999 | MAT | Sundries | L.S. | 35.88 | 2.27 | 81.45 |
- TOTAL
- 5,129.57
- Add 1 % Water charges on “W”
- +51.30
- TOTAL
- 5,180.87
- Add GST on “X” (multiplying factor 0.2127)
- +1,101.97
- TOTAL
- 6,282.84
- Add 15% CPOH on “Y”
- +942.43
- TOTAL
- 7,225.27
- Add Cess @ 1% on “Z”
- +72.25
- Cost of 2.38 sqm.
- 7,297.52
- Cost of 1 sqm.
- 3,066.18
- SAY
- ₹3,066.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 491
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 491. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate