Providing and fixing Pre-laminated flat pressed 3 layer (medium density) particle board or graded wood particle board IS : 3087 marked, with one side decorative and other side balancing lamination Grade I, Type II exterior grade IS : 12823 marked, in shelves with screws and fittings wherever required, edges to be painted with polyurethane primer (fittings to be paid separately)
- Item number
- 9.18.2
- Analysis basis
- 4 nos
- Priced inputs
- 5
- Derived rate
- ₹1,715.20/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.18.2 (Providing and fixing Pre-laminated flat pressed 3 layer (medium density) particle board or graded wood particle board IS : 3087 marked, with one side decorative and other side balancing lamination Grade I, Type II exterior grade IS : 12823 marked, in shelves with screws and fittings wherever required, edges to be painted with polyurethane primer (fittings to be paid separately) 25 mm thick) is derived from 5 priced inputs for 4 nos and works out to ₹1,715.20 each after water charges, GST, CPOH and cess. The full build-up is below.
- 75x20cm shelves = 0.60 sqm.
- 25mm thick particle board
- 4x75x20cm = 0.60sqm.
- Total = 0.63 sqm
- Add wastage @ 5% = 0.03sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7479 | MAT | Prelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 25 mm thickPrelaminated flat pressed three layer or graded wood particle board with one side decorative and other side balancing lamination, (medium density) Grade I, Type II conforming and marked to IS : 12823 (exterior grade) 25 mm thick | sqm | 0.63 | 901.00 | 567.63 |
| 9977 | MAT | Carriage of board | L.S. | 1.82 | 2.27 | 4.13 |
| 0112 | LAB | Carpenter 2nd class | day | 0.11 | 816.00 | 89.76 |
| 0114 | LAB | Beldar | day | 0.06 | 736.00 | 44.16 |
| 9999 | MAT | Sundries, Painting edges & Screws | L.S. | 7.8 | 2.27 | 17.71 |
- TOTAL
- 723.39
- Add 1 % Water charges on “W”
- +7.23
- TOTAL
- 730.62
- Add GST on “X” (multiplying factor 0.2127)
- +155.40
- TOTAL
- 886.02
- Add 15% CPOH on “Y”
- +132.90
- TOTAL
- 1,018.92
- Add Cess @ 1% on “Z”
- +10.19
- Cost of 0.60 sqm.
- 1,029.11
- Cost per sqm.
- 1,715.18
- SAY
- ₹1,715.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 472
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 472. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.