Providing and fixing Pre-laminated flat pressed 3 layer (medium density) particle board or graded wood particle board IS : 3087 marked, with one side decorative and other side balancing lamination Grade I, Type II exterior grade IS : 12823 marked, in shelves with screws and fittings wherever required, edges to be painted with polyurethane primer (fittings to be paid separately)

25 mm thick
Item number
9.18.2
Analysis basis
4 nos
Priced inputs
5
Derived rate
₹1,715.20/ NOS
D-01/RATE ANALYSISITEM 9.18.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.18.2 (Providing and fixing Pre-laminated flat pressed 3 layer (medium density) particle board or graded wood particle board IS : 3087 marked, with one side decorative and other side balancing lamination Grade I, Type II exterior grade IS : 12823 marked, in shelves with screws and fittings wherever required, edges to be painted with polyurethane primer (fittings to be paid separately) 25 mm thick) is derived from 5 priced inputs for 4 nos and works out to ₹1,715.20 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 75x20cm shelves = 0.60 sqm.
  • 25mm thick particle board
  • 4x75x20cm = 0.60sqm.
  • Total = 0.63 sqm
  • Add wastage @ 5% = 0.03sqm.
ANALYSIS OF RATES · ITEM 9.18.2DETAILS OF COST FOR 4 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7479MATPrelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 25 mm thickPrelaminated flat pressed three layer or graded wood particle board with one side decorative and other side balancing lamination, (medium density) Grade I, Type II conforming and marked to IS : 12823 (exterior grade) 25 mm thicksqm0.63901.00567.63
9977MATCarriage of boardL.S.1.822.274.13
0112LABCarpenter 2nd classday0.11816.0089.76
0114LABBeldarday0.06736.0044.16
9999MATSundries, Painting edges & ScrewsL.S.7.82.2717.71
BUILD-UP TO RATE
TOTAL
723.39
Add 1 % Water charges on “W”
+7.23
TOTAL
730.62
Add GST on “X” (multiplying factor 0.2127)
+155.40
TOTAL
886.02
Add 15% CPOH on “Y”
+132.90
TOTAL
1,018.92
Add Cess @ 1% on “Z”
+10.19
Cost of 0.60 sqm.
1,029.11
Cost per sqm.
1,715.18
SAY
₹1,715.20
D-02/SOURCEPRINTED PAGE 472
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
472

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 472. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.