Skip to main content
R/DAR 2023

Providing and fixing stainless steel soft closing spring hinges at 0 degree hinges (hydraulic type) of approved make/brand to cupboard shutters with full threaded steel screws including making necessary recess in board and finished etc. complete as per direction of Engineer-incharge

Item number
9.171
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹272.00/ NO
D-01/RATE ANALYSISITEM 9.171

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.171 (Providing and fixing stainless steel soft closing spring hinges at 0 degree hinges (hydraulic type) of approved make/brand to cupboard shutters with full threaded steel screws including making necessary recess in board and finished etc. complete as per direction of Engineer-incharge) is derived from 4 priced inputs for 10 nos and works out to ₹272.00 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.171DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8228MATSoft closing stainless steel hinges10 sets11,750.001,750.00
8212MATSS screws 30mmStainless steel screws 30 mm100 Nos0.4255.00102.00
9977MATCarriage of materialsL.S.2.732.276.20
0111LABCarpenter 1st classday0.06897.0053.82
BUILD-UP TO RATE
TOTAL
1,912.02
Add 1 % Water charges on “W”
+19.12
TOTAL
1,931.14
Add GST on “X” (multiplying factor 0.2127)
+410.75
TOTAL
2,341.89
Add 15% CPOH on “Y”
+351.28
TOTAL
2,693.17
Add Cess @ 1% on “Z”
+26.93
Cost of 10 nos
2,720.10
Cost of 1 no
272.01
SAY
₹272.00
D-02/SOURCEPRINTED PAGE 708
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
708

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 708. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.