Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing Pre-laminated medium density fibre board IS: 14587:1998 marked, with one side decorative lamination other side balancing lamination Grade-I(exterior grade) in shelves with screws and fittings wherever required, edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand (fittings to be paid separately)

Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick conforming to IS:14587

Item number
9.157.2
Analysis basis
Detail of cost for 4 Nos. 75x20 cm
Priced inputs
6
Derived rate
1,874.70 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.157.2 Providing and fixing Pre-laminated medium density fibre board IS: 14587:1998 marked, with one side decorative lamination other side balancing lamination Grade-I(exterior grade) in shelves with screws and fittings wherever required, edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand (fittings to be paid separately) Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick conforming to IS:14587 — is derived from 6 priced inputs for 4 Nos and works out to ₹1,874.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • shelves = 0.60 sqm
  • 25 mm Thick MDF Board outside laminated =
  • 0.60 sqm
  • Total= 0.63 sqm
  • PVC edge bending tape 2.00 mm thick 4X 0.75
  • =3.00 metre
  • Add wastage @ 5% = 0.03 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2486Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick conforming to IS:14587Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade-I MDF Board 25 mm thick conforming to IS: 14587Materialsqm0.63903.00568.89
2489PVC edge bending tape 2.00 mm thickMaterialmetre322.0066.00
9999Sundries (Carriage of MDF board)MaterialL.S.1.822.274.13
0112Carpenter 2nd classLabourday0.11816.0089.76
0114BeldarLabourday0.06736.0044.16
9999Sundries and screwsMaterialL.S.7.82.2717.71
TOTAL
790.65
Add 1 % Water charges on “W”
7.91
TOTAL
798.56
Add GST on “X” (multiplying factor 0.2127)
169.85
TOTAL
968.41
Add 15% CPOH on “Y”
145.26
TOTAL
1,113.67
Add Cess @ 1% on “Z”
11.14
Cost of 0.60 sqm.
1,124.81
Cost of 1 sqm.
1,874.68
Say
1,874.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 696. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.