CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing casement handle made of zinc alloyed (white powder coated) for uPVC casement window with necessary screws etc. complete

Item number
9.149
Analysis basis
Details of cost for 10 Nos
Priced inputs
4
Derived rate
231.05 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.149 Providing and fixing casement handle made of zinc alloyed (white powder coated) for uPVC casement window with necessary screws etc. complete — is derived from 4 priced inputs for 10 Nos and works out to ₹231.05 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8750Zinc alloy (white powder coated) casement handle for uPVC windowsZinc alloy (white powder coated) casement handle for uPVC window/ doorMaterialeach10150.001,500.00
9977Carriage of materialsMaterialL.S.4.422.2710.03
9999Sundries(Screws)MaterialL.S.32.276.81
0156Carpenter (average)Labourday0.125857.00107.13
TOTAL
1,623.97
Add 1 % Water charges on “W”
16.24
TOTAL
1,640.21
Add GST on “X” (multiplying factor 0.2127)
348.87
TOTAL
1,989.08
Add 15% CPOH on “Y”
298.36
TOTAL
2,287.44
Add Cess @ 1% on “Z”
22.87
Cost of 10 Nos
2,310.31
Cost of 1 No
231.03
Say
231.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 690. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.