Providing & Fixing decorative high pressure laminated sheet of plain / wood grain in gloss / matt/ suede finish with high density protective surface layer and reverse side of adhesive bonding quality conforming to IS : 2046 Type S, including cost of adhesive of approved quality
- Item number
- 9.127.2
- Analysis basis
- 5.00 sqm
- Priced inputs
- 5
- Derived rate
- ₹897.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.127.2 (Providing & Fixing decorative high pressure laminated sheet of plain / wood grain in gloss / matt/ suede finish with high density protective surface layer and reverse side of adhesive bonding quality conforming to IS : 2046 Type S, including cost of adhesive of approved quality 1.0 mm thick) is derived from 5 priced inputs for 5.00 sqm and works out to ₹897.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Decorative laminate = 5.00 sqm
- Total = 5.50 sqm
- Add wastage @ 10% = 0.50 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8727 | MAT | 1.0mm thick decorative laminated sheet1.0 mm thick decorative laminated sheet | sqm | 5.5 | 323.00 | 1,776.50 |
| 9999 | MAT | Adhesive | L.S. | 195 | 2.27 | 442.65 |
| 0111 | LAB | Carpenter 1st class | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | Sundries i/c nails etc. | L.S. | 52 | 2.27 | 118.04 |
- TOTAL
- 3,153.69
- Add 1 % Water charges on “W”
- +31.54
- TOTAL
- 3,185.23
- Add GST on “X” (multiplying factor 0.2127)
- +677.50
- TOTAL
- 3,862.73
- Add 15% CPOH on “Y”
- +579.41
- TOTAL
- 4,442.14
- Add Cess @ 1% on “Z”
- +44.42
- Cost for 5.00 sqm
- 4,486.56
- Cost for 1 sqm
- 897.31
- SAY
- ₹897.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 599
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 599. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.