Providing and fixing partition upto ceiling height consisting of G.I. frame and required board, including providing and fixing of frame work made of special section power pressed/ roll form G.I. sheet with zinc coating of 120 gms/sqm(both side inclusive), consisting of floor and ceiling channel 50mm wide having equal flanges of 32 mm and 0.50 mm thick, fixed to the floor and ceiling at the spacing of 610 mm centre to centre with dash fastener of 12.5 mm dia meter 50 mm length or suitable anchor fastener or metal screws with nylon plugs and the studs 48 mm wide having one flange of 34 mm and other flange 36 mm and 0.50 mm thick fixed vertically within flanges of floor and ceiling channel and placed at a spacing of 610 mm centre to centre by 6 mm dia bolts and nuts, including fixing of studs along both ends of partition fixed flush to wall with suitable anchor fastener or metal screws with nylon plugs at spacing of 450 mm centre to centre, and fixing of boards to both side of frame work by 25 mm long dry wall screws on studs, floor and ceiling channels at the spacing of 300 mm centre to centre. The boards are to be fixed to the frame work with joints staggered to avoid through cracks, M.S. fixing channel of 99 mm width (0.9 mm thick having two flanges of 9.5 mm each) to be provided at the horizontal joints of two boards, fixed to the studs using metal to metal flat head screws, including jointing and finishing to a flush finish with recommended jointing compound, jointing tape, angle beads at corners (25 mm x 25 mm x 0.5 mm), joint finisher and two coats of primer suitable for board as per manufacture’s specification and direction of engineer in charge all complete

66mm overall thickness Partition with 8mm thick double skin Calcium Silicate Board made with Calcareous & Siliceous materials reinforced with cellulose fiber manufactured through autoclaving process with Compressive Strength 225 kg/sq.cm, Bending Strength 100 kg./ sq.cm
Item number
9.105.3
Analysis basis
Details of cost for 6.00x3.65 = 21.9 sqm
Priced inputs
18
Derived rate
₹2,225.00
D-01/RATE ANALYSISITEM 9.105.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.105.3 (Providing and fixing partition upto ceiling height consisting of G.I. frame and required board, including providing and fixing of frame work made of special section power pressed/ roll form G.I. sheet with zinc coating of 120 gms/sqm(both side inclusive), consisting of floor and ceiling channel 50mm wide having equal flanges of 32 mm and 0.50 mm thick, fixed to the floor and ceiling at the spacing of 610 mm centre to centre with dash fastener of 12.5 mm dia meter 50 mm length or suitable anchor fastener or metal screws with nylon plugs and the studs 48 mm wide having one flange of 34 mm and other flange 36 mm and 0.50 mm thick fixed vertically within flanges of floor and ceiling channel and placed at a spacing of 610 mm centre to centre by 6 mm dia bolts and nuts, including fixing of studs along both ends of partition fixed flush to wall with suitable anchor fastener or metal screws with nylon plugs at spacing of 450 mm centre to centre, and fixing of boards to both side of frame work by 25 mm long dry wall screws on studs, floor and ceiling channels at the spacing of 300 mm centre to centre. The boards are to be fixed to the frame work with joints staggered to avoid through cracks, M.S. fixing channel of 99 mm width (0.9 mm thick having two flanges of 9.5 mm each) to be provided at the horizontal joints of two boards, fixed to the studs using metal to metal flat head screws, including jointing and finishing to a flush finish with recommended jointing compound, jointing tape, angle beads at corners (25 mm x 25 mm x 0.5 mm), joint finisher and two coats of primer suitable for board as per manufacture’s specification and direction of engineer in charge all complete 66mm overall thickness Partition with 8mm thick double skin Calcium Silicate Board made with Calcareous & Siliceous materials reinforced with cellulose fiber manufactured through autoclaving process with Compressive Strength 225 kg/sq.cm, Bending Strength 100 kg./ sq.cm) is derived from 18 priced inputs and works out to ₹2,225.00 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (Partition Panel)
  • 2x6.00x3.65=43.80sqm
  • 50mm floor and ceiling channel 2x6.00 =12m
  • 48mm stud-72x34x36x0.5mm
  • (6.00/0.61)+1 = 11x3.65 = 40.15m
  • [(3.65/0.30)+1]x11x2 = 308
  • [(6.00/0.30)+1]x2x2=84
  • Total = 392
  • [(6.00/0.61)+1]x2=22
  • [(3.65/0.45)+1]x2= 18
  • (88/100)x21.9 = 19.27
  • (22/100)x21.90=4.82
  • (120m roll) (300/100)x21.90/120 = 0.584 Nos
  • (36/100)x21.90 = 7.88 litre
  • 11x2x2=44
  • Labour for 21.90 sqm.
  • 0.3x21.90=6.57
  • 0.13x21.90=2.847
  • 0.05x21.90=1.095
  • 0.35x21.90=7.665
ANALYSIS OF RATES · ITEM 9.105.3DETAILS OF COST FOR 6.00X3.65 = 21.9 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8699MAT8 mm thick tapered edge calcium silicate board .8 mm thick tapered edge calcium silicate boardsqm43.8297.0013,008.60
7367MATGalvanised M.S. sheet 0.5 mm thick pressed channel section of size 50x32 mmmetre1265.00780.00
7369MATGalvanised M.S. sheet 0.50 mm thick pressed stud. 48x34x36 mmGalvanised M.S. sheet 0.50 mm thick pressed stud : 48x34x36 mmmetre40.1576.003,051.40
7020MATAll drive screws ( for gypsum board)All drive screws (for gypsum board)100 Nos3.9263.00246.96
7388MATDash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia boltDash hold fastener 12.5 mm dia, 50 mm long with 6 mm dia bolteach2210.00220.00
7048MATRawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)each1824.00432.00
0869MATPlaster of Pariskilogram19.277.00134.89
0763MATGluekilogram4.8280.00385.60
7018MATJoint tape rollroll0.58495.0055.48
7021MATPrimer ( for gypsum board)Primer (for gypsum board)litre7.8875.00591.00
1022MATGalvanised steel bolts & nuts 6 mm dia and 25 mmlong round head with slotsGalvanised steel bolts & nuts 6 mm dia and 25 mm long round head with slots10 Nos4.438.00167.20
1211MATG.I. plain washer for seam bolts100 Nos0.4432.0014.08
9977MATSundries carriageL.S.522.27118.04
9999MATSundries scaffoldingL.S.1302.27295.10
0111LABCarpenter 1st classday6.57897.005,893.29
0112LABCarpenter 2nd classday2.847816.002,323.15
0131LABPainterday1.095816.00893.52
0114LABBeldarday7.665736.005,641.44
BUILD-UP TO RATE
TOTAL
34,251.75
Add 1 % Water charges on “W”
+342.52
TOTAL
34,594.27
Add GST on “X” (multiplying factor 0.2127)
+7,358.20
TOTAL
41,952.47
Add 15% CPOH on “Y”
+6,292.87
TOTAL
48,245.34
Add Cess @ 1% on “Z”
+482.45
Cost for 21.90 sqm
48,727.79
Cost for 1 sqm.
2,225.01
SAY
₹2,225.00
D-02/SOURCEPRINTED PAGE 576
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
576

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 576. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.