Providing and fixing bright finished brass 100 mm mortice latch and lock, ISI marked, with six levers and a pair of anodised (anodic coating not less than grade AC 10 as per IS : 1868) aluminium lever handles of approved quality with necessary screws etc. complete

Item number
9.103
Analysis basis
1 lock
Priced inputs
4
Derived rate
₹868.95/ LOCK
D-01/RATE ANALYSISITEM 9.103

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.103 (Providing and fixing bright finished brass 100 mm mortice latch and lock, ISI marked, with six levers and a pair of anodised (anodic coating not less than grade AC 10 as per IS : 1868) aluminium lever handles of approved quality with necessary screws etc. complete) is derived from 4 priced inputs for 1 lock and works out to ₹868.95 per lock after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.103DETAILS OF COST FOR 1 LOCK
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7001MATBrass 100mm mortice latch and lock with6 levers without pair of handlesBrass 100 mm mortice latch and lock with 6 levers without pair of handleseach1211.00211.00
7003MATPair of Anodised Aluminium lever handles for 100mm mortice latch and lockPair of Anodised Aluminium lever handles for 100 mm mortice latch and lockeach1237.00237.00
0111LABCarpenter 1st classday0.17897.00152.49
9988MATSundries including carriage of materialsL.S.4.552.2710.33
BUILD-UP TO RATE
TOTAL
610.82
Add 1 % Water charges on “W”
+6.11
TOTAL
616.93
Add GST on “X” (multiplying factor 0.2127)
+131.22
TOTAL
748.15
Add 15% CPOH on “Y”
+112.22
TOTAL
860.37
Add Cess @ 1% on “Z”
+8.60
Cost of 1 lock
868.97
SAY
₹868.95
D-02/SOURCEPRINTED PAGE 572
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
572

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 572. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.