CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing bright finished brass 100 mm mortice latch and lock, ISI marked, with six levers and a pair of anodised (anodic coating not less than grade AC 10 as per IS : 1868) aluminium lever handles of approved quality with necessary screws etc. complete
- Item number
- 9.103
- Analysis basis
- Details of cost for 1 lock
- Priced inputs
- 4
- Derived rate
- ₹868.95 / lock
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.103 — Providing and fixing bright finished brass 100 mm mortice latch and lock, ISI marked, with six levers and a pair of anodised (anodic coating not less than grade AC 10 as per IS : 1868) aluminium lever handles of approved quality with necessary screws etc. complete — is derived from 4 priced inputs for 1 lock and works out to ₹868.95 per lock after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7001 | Brass 100mm mortice latch and lock with6 levers without pair of handlesBrass 100 mm mortice latch and lock with 6 levers without pair of handlesMaterial | each | 1 | 211.00 | 211.00 |
| 7003 | Pair of Anodised Aluminium lever handles for 100mm mortice latch and lockPair of Anodised Aluminium lever handles for 100 mm mortice latch and lockMaterial | each | 1 | 237.00 | 237.00 |
| 0111 | Carpenter 1st classLabour | day | 0.17 | 897.00 | 152.49 |
| 9988 | Sundries including carriage of materialsMaterial | L.S. | 4.55 | 2.27 | 10.33 |
- TOTAL
- 610.82
- Add 1 % Water charges on “W”
- 6.11
- TOTAL
- 616.93
- Add GST on “X” (multiplying factor 0.2127)
- 131.22
- TOTAL
- 748.15
- Add 15% CPOH on “Y”
- 112.22
- TOTAL
- 860.37
- Add Cess @ 1% on “Z”
- 8.60
- Cost of 1 lock
- 868.97
- Say
- 868.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 572. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.