Skip to main content
R/DAR 2023

Providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Female Threaded Elbow 90°

For 15.88 mm outer dia x 15 mm nominal dia threaded
Item number
18.99.1
Analysis basis
1 no
Priced inputs
1
Derived rate
₹270.30/ NO
D-01/RATE ANALYSISITEM 18.99.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.99.1 (Providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Female Threaded Elbow 90° For 15.88 mm outer dia x 15 mm nominal dia threaded) is derived from 1 priced inputs for 1 no and works out to ₹270.30 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.99.1DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8917MATSS Female Threaded Elbow 90° for 15.88 mm outer dia X 15 mm nominal dia threadedSS Female Threaded Elbow 90° for 15.88 mm outer dia X 15 mm nominal dia threadedeach1190.00190.00
BUILD-UP TO RATE
TOTAL
190.00
Add 1 % Water charges on “W”
+1.90
TOTAL
191.90
Add GST on “X” (multiplying factor 0.2127)
+40.82
TOTAL
232.72
Add 15% CPOH on “Y”
+34.91
TOTAL
267.63
Add Cess @ 1% on “Z”
+2.68
Cost of 1 no.
270.31
SAY
₹270.30
D-02/SOURCEPRINTED PAGE 1668
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1668

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1668. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.