Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Equal Tee
- Item number
- 18.92A.3
- Analysis basis
- 1 no
- Priced inputs
- 1
- Derived rate
- ₹1,145.25/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.92A.3 (Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Equal Tee For 28 mm outer dia pipe) is derived from 1 priced inputs for 1 no and works out to ₹1,145.25 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3899 | MAT | Equal Tee for 28 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312Equal Tee for 28 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard | each | 1 | 805.00 | 805.00 |
- TOTAL
- 805.00
- Add 1 % Water charges on “W”
- +8.05
- TOTAL
- 813.05
- Add GST on “X” (multiplying factor 0.2127)
- +172.94
- TOTAL
- 985.99
- Add 15% CPOH on “Y”
- +147.90
- TOTAL
- 1,133.89
- Add Cess @ 1% on “Z”
- +11.34
- Cost of 1 no.
- 1,145.23
- SAY
- ₹1,145.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1625
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1625. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.