Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work

32 mm nominal dia Pipes
Item number
18.9.4
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹438.60/ METRE
D-01/RATE ANALYSISITEM 18.9.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.9.4 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work 32 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹438.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 30 x P / 100
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.9.4DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8639MATChlorinated Polyvinyl - chloride (CPVC) pipe 32 mm nominal diametre10140.001,400.00
0116LABFitter (grade 1)day0.12897.00107.64
0114LABBeldarday0.25736.00184.00
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 30% for fittings and wastage etc. on (P)
+420.00
TOTAL
3,083.16
Add 1 % Water charges on “W”
+30.83
TOTAL
3,113.99
Add GST on “X” (multiplying factor 0.2127)
+662.35
TOTAL
3,776.34
Add 15% CPOH on “Y”
+566.45
TOTAL
4,342.79
Add Cess @ 1% on “Z”
+43.43
Cost of 10 metre
4,386.22
Cost of 1 metre
438.62
SAY
₹438.60
D-02/SOURCEPRINTED PAGE 1422
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1422

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1422. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.