Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work
- Item number
- 18.9.4
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹438.60/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.9.4 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work 32 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹438.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 30 x P / 100
- Trenching and refilling etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8639 | MAT | Chlorinated Polyvinyl - chloride (CPVC) pipe 32 mm nominal dia | metre | 10 | 140.00 | 1,400.00 |
| 0116 | LAB | Fitter (grade 1) | day | 0.12 | 897.00 | 107.64 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
| 0115 | LAB | Coolie | day | 0.66 | 736.00 | 485.76 |
- Add 30% for fittings and wastage etc. on (P)
- +420.00
- TOTAL
- 3,083.16
- Add 1 % Water charges on “W”
- +30.83
- TOTAL
- 3,113.99
- Add GST on “X” (multiplying factor 0.2127)
- +662.35
- TOTAL
- 3,776.34
- Add 15% CPOH on “Y”
- +566.45
- TOTAL
- 4,342.79
- Add Cess @ 1% on “Z”
- +43.43
- Cost of 10 metre
- 4,386.22
- Cost of 1 metre
- 438.62
- SAY
- ₹438.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1422
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1422. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.