Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Sleeve/Slip Coupling/ Socket
- Item number
- 18.89A.5
- Analysis basis
- 1 no
- Priced inputs
- 1
- Derived rate
- ₹1,066.95/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.89A.5 (Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Sleeve/Slip Coupling/ Socket For 42 mm outer dia pipe) is derived from 1 priced inputs for 1 no and works out to ₹1,066.95 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3889 | MAT | Sleeve/ Slip Coupling / Socket 42 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312Sleeve/Slip Coupling / Socket 42 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard | each | 1 | 750.00 | 750.00 |
- TOTAL
- 750.00
- Add 1 % Water charges on “W”
- +7.50
- TOTAL
- 757.50
- Add GST on “X” (multiplying factor 0.2127)
- +161.12
- TOTAL
- 918.62
- Add 15% CPOH on “Y”
- +137.79
- TOTAL
- 1,056.41
- Add Cess @ 1% on “Z”
- +10.56
- Cost of 1 no.
- 1,066.97
- SAY
- ₹1,066.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1616
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1616. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.