Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per dirction of Engineer-in-charge. Reducer

For 42 mm x 22 mm outer dia pipe
Item number
18.88A.6
Analysis basis
1 no
Priced inputs
1
Derived rate
₹960.30/ NO
D-01/RATE ANALYSISITEM 18.88A.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.88A.6 (Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per dirction of Engineer-in-charge. Reducer For 42 mm x 22 mm outer dia pipe) is derived from 1 priced inputs for 1 no and works out to ₹960.30 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.88A.6DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3879MATReducer for 42 mm x 22 mm outer Dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312Reducer for 42 mm X 22 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312 standardeach1675.00675.00
BUILD-UP TO RATE
TOTAL
675.00
Add 1 % Water charges on “W”
+6.75
TOTAL
681.75
Add GST on “X” (multiplying factor 0.2127)
+145.01
TOTAL
826.76
Add 15% CPOH on “Y”
+124.01
TOTAL
950.77
Add Cess @ 1% on “Z”
+9.51
Cost of 1 no.
960.28
SAY
₹960.30
D-02/SOURCEPRINTED PAGE 1611
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1611

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1611. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.