Providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of required dia as per dirction of Engineer-in-charge. Reducer
- Item number
- 18.88.13
- Analysis basis
- 1 no
- Priced inputs
- 1
- Derived rate
- ₹643.05/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.88.13 (Providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of required dia as per dirction of Engineer-in-charge. Reducer For 48.60 mm x 28.58 mm outer dia pipe) is derived from 1 priced inputs for 1 no and works out to ₹643.05 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8803 | MAT | Reducer for 48.60 mm X 28.58 mm outer Dia SS pipe | each | 1 | 452.00 | 452.00 |
- TOTAL
- 452.00
- Add 1 % Water charges on “W”
- +4.52
- TOTAL
- 456.52
- Add GST on “X” (multiplying factor 0.2127)
- +97.10
- TOTAL
- 553.62
- Add 15% CPOH on “Y”
- +83.04
- TOTAL
- 636.66
- Add Cess @ 1% on “Z”
- +6.37
- Cost of 1 no.
- 643.03
- SAY
- ₹643.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1608
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1608. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.