CPWD Analysis of Rates · Water Supply

Providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of required dia as per dirction of Engineer-in-charge. Reducer

For 22.22 mm x 15.88 mm outer dia pipe

Item number
18.88.1
Analysis basis
Details of cost for 1 no.
Priced inputs
1
Derived rate
139.40 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.88.1 Providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of providing and fixing required Stainless Steel Fitting of press fit design of grade AISI 304 conforming to JWWA G116 standard with V-profile or M-profile and with O-ring sealing gasket of EPDM material of required dia as per dirction of Engineer-in-charge. Reducer For 22.22 mm x 15.88 mm outer dia pipe — is derived from 1 priced inputs for 1 no and works out to ₹139.40 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8791Reducer for 22.22 mm X 15.88 mm outer Dia SS pipeMaterialeach198.0098.00
TOTAL
98.00
Add 1 % Water charges on “W”
0.98
TOTAL
98.98
Add GST on “X” (multiplying factor 0.2127)
21.05
TOTAL
120.03
Add 15% CPOH on “Y”
18.00
TOTAL
138.03
Add Cess @ 1% on “Z”
1.38
Cost of 1 no.
139.41
Say
139.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1604. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works