Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Coupling/Socket

For 42 mm outer dia pipe

Item number
18.87A.5
Analysis basis
Details of cost for 1 no.
Priced inputs
1
Derived rate
846.45 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.87A.5 Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Coupling/Socket For 42 mm outer dia pipe — is derived from 1 priced inputs for 1 no and works out to ₹846.45 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
3872Coupling/Socket fittings for 42 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312Coupling/Socket fittings for 42 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312 standardMaterialeach1595.00595.00
TOTAL
595.00
Add 1 % Water charges on “W”
5.95
TOTAL
600.95
Add GST on “X” (multiplying factor 0.2127)
127.82
TOTAL
728.77
Add 15% CPOH on “Y”
109.32
TOTAL
838.09
Add Cess @ 1% on “Z”
8.38
Cost of 1 no.
846.47
Say
846.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1603. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works