Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Coupling/Socket
- Item number
- 18.87A.3
- Analysis basis
- 1 no
- Priced inputs
- 1
- Derived rate
- ₹497.90/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.87A.3 (Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Coupling/Socket For 28 mm outer dia pipe) is derived from 1 priced inputs for 1 no and works out to ₹497.90 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3870 | MAT | Coupling/Socket fittings for 28 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312Coupling/Socket fittings for 28 mm outer dia SS pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard | each | 1 | 350.00 | 350.00 |
- TOTAL
- 350.00
- Add 1 % Water charges on “W”
- +3.50
- TOTAL
- 353.50
- Add GST on “X” (multiplying factor 0.2127)
- +75.19
- TOTAL
- 428.69
- Add 15% CPOH on “Y”
- +64.30
- TOTAL
- 492.99
- Add Cess @ 1% on “Z”
- +4.93
- Cost of 1 no.
- 497.92
- SAY
- ₹497.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1603
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1603. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.