Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00m spacing and also including cutting of chases and making good the walls including testing of joints complete as per direction of Engineer -in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Concealed Pipe
- Item number
- 18.86A.2
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹1,227.25/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.86A.2 (Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00m spacing and also including cutting of chases and making good the walls including testing of joints complete as per direction of Engineer -in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Concealed Pipe 22 mm Outer dia pipes) is derived from 5 priced inputs for 10 metre and works out to ₹1,227.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 3xP/ 100
- Making chases upto 7.5x7.5 cm.in walls and
- making good the same
- 2xP/ 100
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3863 | MAT | SS pipe 316L grade as per IS 6911:2017 with press fit technology conforming to EN-10312 standards 22 mm outer diaSS pipe 316L grade as per IS 6911:2017 with press fit technology and conforming to EN-10312 standard 22 mm outer dia | metre | 10 | 560.00 | 5,600.00 |
| SUB | Rate as per Item No.18.78 of SH: WATER SUPPLYRate as per item 18.78 | metre | 10 | 202.90 | 2,029.00 | |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 0.66 | 816.00 | 538.56 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
- Add 3% for pipe inserted into fitting and wastage etc. on P
- +168.00
- Add 2% for special T&P and sundries etc. on P
- +112.00
- TOTAL
- 9,229.33
- Add 1 % Water charges on “W-A”
- +72.00
- TOTAL
- 9,301.33
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,546.82
- TOTAL
- 10,848.15
- Add 15% CPOH on “Y-A”
- +1,322.87
- TOTAL
- 12,171.02
- Add Cess @ 1% on “Z-A”
- +101.42
- Cost of 10 metre
- 12,272.44
- Cost of 1 metre
- 1,227.24
- SAY
- ₹1,227.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1599
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1599. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.