Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing Stainless Steel pipe and fitting of grade AISI 304 as per JIS standard 3448 complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00m spacing and also including cutting of chases and making good the walls including testing of joints complete as per direction of Engineer -in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Concealed Pipe

15.88 mm outer dia Pipe

Item number
18.86.1
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
622.25 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.86.1 Providing and fixing Stainless Steel pipe and fitting of grade AISI 304 as per JIS standard 3448 complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00m spacing and also including cutting of chases and making good the walls including testing of joints complete as per direction of Engineer -in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Concealed Pipe 15.88 mm outer dia Pipe — is derived from 5 priced inputs for 10 metre and works out to ₹622.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Making chases upto 7.5x7.5 cm.in walls and
  • making good the same
  • 3xP/ 100
  • 2xP/ 100
CodeInputUnitQuantityRate (INR)Amount (INR)
8779SS pipe 304 grades with press fit technology as per JIS 3448 standard 15.88 mm outer diaMaterialmetre10155.001,550.00
Rate as per Item No.18.78 of SH:WATER SUPPLYRate as per item 18.78Sub-analysismetre10202.902,029.00
0116Fitter (grade 1)Labourday0.33897.00296.01
0117Assistant Fitter or 2nd class FitterLabourday0.66816.00538.56
0114BeldarLabourday0.66736.00485.76
Add 3% for pipe inserted into fitting and wastage etc. on P
46.50
Add 2% for special T&P and sundries etc. on P
31.00
TOTAL
4,976.83
Add 1 % Water charges on “W-A”
29.48
TOTAL
5,006.31
Add GST on “X-A” (multiplying factor 0.2127)
633.27
TOTAL
5,639.58
Add 15% CPOH on “Y-A”
541.59
TOTAL
6,181.17
Add Cess @ 1% on “Z-A”
41.52
Cost of 10 metre
6,222.69
Cost of 1 metre
622.27
Say
622.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1598. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works