Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall

15 mm outer dia pipe
Item number
18.85A.1
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹704.05/ METRE
D-01/RATE ANALYSISITEM 18.85A.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.85A.1 (Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall 15 mm outer dia pipe) is derived from 5 priced inputs for 10 metre and works out to ₹704.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 3xP / 100
  • 2 xP / 100
ANALYSIS OF RATES · ITEM 18.85A.1DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3862MATSS pipe 316L grade as per IS 6911:2017 with press fit technology conforming to EN-10312 standards 15 mm outer diaSS pipe 316L grade as per IS 6911:2017 with press fit technology and conforming to EN-10312 standard 15 mm outer diametre10345.003,450.00
9999MATCement, sand and gritL.S.2.732.276.20
0116LABFitter (grade 1)day0.33897.00296.01
0117LABAssistant Fitter or 2nd class Fitterday0.66816.00538.56
0114LABBeldarday0.66736.00485.76
BUILD-UP TO RATE
Add 3% for pipe inserted into fitting and wastage etc. on P
+103.50
Add 2% for special T&P and sundries etc. on P
+69.00
TOTAL
4,949.03
Add 1 % Water charges on “W”
+49.49
TOTAL
4,998.52
Add GST on “X” (multiplying factor 0.2127)
+1,063.19
TOTAL
6,061.71
Add 15% CPOH on “Y”
+909.26
TOTAL
6,970.97
Add Cess @ 1% on “Z”
+69.71
Cost of 10 metre
7,040.68
Cost of 1 metre
704.07
SAY
₹704.05
D-02/SOURCEPRINTED PAGE 1594
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1594

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1594. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.