Labour for cutting C.I. pipe with steel saw

150 mm diameter C.I. pipe
Item number
18.83.4
Analysis basis
one cut
Priced inputs
3
Derived rate
₹365.70/ ONE CUT
D-01/RATE ANALYSISITEM 18.83.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.83.4 (Labour for cutting C.I. pipe with steel saw 150 mm diameter C.I. pipe) is derived from 3 priced inputs for one cut and works out to ₹365.70 per one cut after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.83.4DETAIL OF COST FOR ONE CUT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0116LABFitter (grade 1)day0.15897.00134.55
0114LABBeldarday0.15736.00110.40
9999MATSundriesL.S.5.332.2712.10
BUILD-UP TO RATE
TOTAL
257.05
Add 1 % Water charges on “W”
+2.57
TOTAL
259.62
Add GST on “X” (multiplying factor 0.2127)
+55.22
TOTAL
314.84
Add 15% CPOH on “Y”
+47.23
TOTAL
362.07
Add Cess @ 1% on “Z”
+3.62
Cost of each cut
365.69
SAY
₹365.70
D-02/SOURCEPRINTED PAGE 1587
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1587

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1587. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.