Labour for cutting C.I. pipe with steel saw

100 mm diameter C.I. pipe
Item number
18.83.2
Analysis basis
one cut
Priced inputs
3
Derived rate
₹194.70/ ONE CUT
D-01/RATE ANALYSISITEM 18.83.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.83.2 (Labour for cutting C.I. pipe with steel saw 100 mm diameter C.I. pipe) is derived from 3 priced inputs for one cut and works out to ₹194.70 per one cut after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.83.2DETAIL OF COST FOR ONE CUT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0116LABFitter (grade 1)day0.08897.0071.76
0114LABBeldarday0.08736.0058.88
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
136.84
Add 1 % Water charges on “W”
+1.37
TOTAL
138.21
Add GST on “X” (multiplying factor 0.2127)
+29.40
TOTAL
167.61
Add 15% CPOH on “Y”
+25.14
TOTAL
192.75
Add Cess @ 1% on “Z”
+1.93
Cost of each cut
194.68
SAY
₹194.70
D-02/SOURCEPRINTED PAGE 1587
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1587

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1587. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.