Dismantling old C.I. pipes including excavation and refilling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, including stacking of pipes at site lead up to 50 metre

300 mm diameter C.I. pipe
Item number
18.82.7
Analysis basis
40.26 m
Priced inputs
7
Derived rate
₹497.80/ M
D-01/RATE ANALYSISITEM 18.82.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.82.7 (Dismantling old C.I. pipes including excavation and refilling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, including stacking of pipes at site lead up to 50 metre: 300 mm diameter C.I. pipe) is derived from 7 priced inputs for 40.26 m and works out to ₹497.80 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • joints.
  • Earth work in excavation for dismantling
  • pipes including refilling of excavated earth
  • 1x40.26x.70x0.75 m=21.14 cum
  • =(-) 3.36 cum
  • Total= 17.78 cum
  • Breaking lead caulked joints, blocks and
  • stacking
  • Deduct for pipe 1x40.26x3.14/4x(0.326)²
ANALYSIS OF RATES · ITEM 18.82.7DETAILS OF COST FOR 40.26 M OR 11 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUB(Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1cum17.78260.304,628.13
SUB(Rate as per item No.2.25 of SH Earth work)Rate as per item 2.25cum17.78196.003,484.88
0761MATFuel woodquintal1.12550.00616.00
0771MATKerosene oillitre1.51550.0075.75
0117LABAssistant Fitter or 2nd class Fitterday1.5816.001,224.00
0114LABBeldarday8.5736.006,256.00
9988MATSundries and carriageL.S.94.122.27213.65
BUILD-UP TO RATE
TOTAL
16,498.41
Add 1 % Water charges on “W-A”
+83.85
TOTAL
16,582.26
Add GST on “X-A” (multiplying factor 0.2127)
+1,801.41
TOTAL
18,383.67
Add 15% CPOH on “Y-A”
+1,540.60
TOTAL
19,924.27
Add Cess @ 1% on “Z-A”
+118.11
Cost of 40.26 metre
20,042.38
Cost of one metre
497.82
SAY
₹497.80
D-02/SOURCEPRINTED PAGE 1582
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1582

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1582. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate