CPWD Analysis of Rates · Water Supply

Dismantling old C.I. pipes including excavation and refilling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, including stacking of pipes at site lead up to 50 metre

500 mm diameter C.I. pipe

Item number
18.82.11
Analysis basis
Details of cost for 40.26 m or 11 nos. joints.
Priced inputs
7
Derived rate
649.45 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.82.11 Dismantling old C.I. pipes including excavation and refilling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, including stacking of pipes at site lead up to 50 metre: 500 mm diameter C.I. pipe — is derived from 7 priced inputs for 40.26 m and works out to ₹649.45 per m after water charges, GST, CPOH and cess. The full build-up is below.

  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x.90x0.75 m=27.18 cum
  • 8.94 cum
  • Total= 18.24 cum
  • Breaking lead caulked joints, blocks and
  • stacking
  • Deduct for pipe 1x40.26x3.14/4x(0.532)² =(-)
CodeInputUnitQuantityRate (INR)Amount (INR)
(Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1Sub-analysiscum18.24260.304,747.87
(Rate as per item No.2.25 of SH Earth work)Rate as per item 2.25Sub-analysiscum18.24196.003,575.04
0761Fuel woodMaterialquintal1.492550.00820.60
0771Kerosene oilMateriallitre2.65250.00132.60
0117Assistant Fitter or 2nd class FitterLabourday2.5816.002,040.00
0114BeldarLabourday12.5736.009,200.00
9988Sundries and carriageMaterialL.S.147.942.27335.82
TOTAL
20,851.93
Add 1 % Water charges on “W-A”
125.29
TOTAL
20,977.22
Add GST on “X-A” (multiplying factor 0.2127)
2,691.57
TOTAL
23,668.79
Add 15% CPOH on “Y-A”
2,301.88
TOTAL
25,970.67
Add Cess @ 1% on “Z-A”
176.48
Cost of 40.26 metre
26,147.15
Cost of one metre
649.46
Say
649.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1585. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.