Extra for every operation of disinfecting the C.I. main by flushing with water containing bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including getting the samples of water tested in the municipal laboratory

200 mm diameter C.I. pipe
Item number
18.81.5
Analysis basis
100 metres
Priced inputs
4
Derived rate
₹1,753.10/ METRES
D-01/RATE ANALYSISITEM 18.81.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.81.5 (Extra for every operation of disinfecting the C.I. main by flushing with water containing bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including getting the samples of water tested in the municipal laboratory: 200 mm diameter C.I. pipe) is derived from 4 priced inputs for 100 metres and works out to ₹1,753.10 per metres after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.81.5DETAILS OF COST FOR 100 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1301MATBleaching powderquintal0.0161,700.0027.20
0116LABFitter (grade 1)day0.58897.00520.26
0114LABBeldarday0.9736.00662.40
9999MATSundries including testing of samplesL.S.9.882.2722.43
BUILD-UP TO RATE
TOTAL
1,232.29
Add 1 % Water charges on “W”
+12.32
TOTAL
1,244.61
Add GST on “X” (multiplying factor 0.2127)
+264.73
TOTAL
1,509.34
Add 15% CPOH on “Y”
+226.40
TOTAL
1,735.74
Add Cess @ 1% on “Z”
+17.36
Cost of 100 metre
1,753.10
SAY
₹1,753.10
D-02/SOURCEPRINTED PAGE 1575
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1575

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1575. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.