Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings and fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge. Concealed work, including cutting chases and making good the walls etc

20 mm nominal dia Pipes
Item number
18.8.2
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹537.60/ METRE
D-01/RATE ANALYSISITEM 18.8.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.8.2 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings and fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge. Concealed work, including cutting chases and making good the walls etc 20 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹537.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 75 x P / 100
  • Making chases upto 7.5 x 7.5 cm. in walls
  • and making good the same
ANALYSIS OF RATES · ITEM 18.8.2DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8637MATChlorinated Polyvinyl - chloride (CPVC) pipe 20 mm nominal diametre1059.00590.00
SUBRate as per item no. 18.78 Of SH: Water SupplyRate as per item 18.78metre10202.902,029.00
0116LABFitter (grade 1)day0.33897.00296.01
0117LABAssistant Fitter or 2nd class Fitterday0.66816.00538.56
0114LABBeldarday0.66736.00485.76
BUILD-UP TO RATE
Add 75% for fittings, clamps and wastage etc. on (P)
+442.50
TOTAL
4,381.83
Add 1 % Water charges on “W-A”
+23.53
TOTAL
4,405.36
Add GST on “X-A” (multiplying factor 0.2127)
+505.45
TOTAL
4,910.81
Add 15% CPOH on “Y-A”
+432.27
TOTAL
5,343.08
Add Cess @ 1% on “Z-A”
+33.14
Cost of 10 metre
5,376.22
Cost of 1 metre
537.62
SAY
₹537.60
D-02/SOURCEPRINTED PAGE 1419
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1419

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1419. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.