CPWD Analysis of Rates · Water Supply

Providing, laying, jointing and testing S&S Centrifugally Cast Ductile Iron double chamber Class K-9 pressure pipes conforming to IS 8329:2000 with restrained joints (bolt less), all complete

100 mm nominal dia pipe

Item number
18.72A.1
Analysis basis
Details of cost for 10 metre
Priced inputs
6
Derived rate
1,870.75 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72A.1 Providing, laying, jointing and testing S&S Centrifugally Cast Ductile Iron double chamber Class K-9 pressure pipes conforming to IS 8329:2000 with restrained joints (bolt less), all complete 100 mm nominal dia pipe — is derived from 6 priced inputs for 10 metre and works out to ₹1,870.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 100 mm nominal dia Centrifugally Cast
  • Ductile Iron restrained joint class K9 pipes
  • (in 5.5 m lengths)
  • Weight of 1 m pipes = 18.65 Kg
  • Weight of 10 m pipes = 186.5 Kg
  • Labour for laying and jointing
CodeInputUnitQuantityRate (INR)Amount (INR)
7591Centrifugally Cast DI class K9 pipe including double chamber restraining arrangements (bolt less) 100 mm nominal dia pipeCentrifugally Cast DI class K9 pipe including double chamber restraining arrangements (bolt less) 100 mm nominal dia pipeMaterialmetre101,256.0012,560.00
7606Rubber Gasket of EPDM quality for 100 mm nominal dia DI pipeRubber Gasket of EPDM quality for 100 mm nominal dia pipeMaterialeach229.0058.00
0116Fitter (grade 1)Labourday0.06897.0053.82
0117Assistant Fitter or 2nd class FitterLabourday0.12816.0097.92
0114BeldarLabourday0.5736.00368.00
9999SundriesMaterialL.S.5.42.2712.26
TOTAL
13,150.00
Add 1 % Water charges on “W”
131.50
TOTAL
13,281.50
Add GST on “X” (multiplying factor 0.2127)
2,824.98
TOTAL
16,106.48
Add 15% CPOH on “Y”
2,415.97
TOTAL
18,522.45
Add Cess @ 1% on “Z”
185.22
Cost of 10 metre
18,707.67
Cost of 1.00 metre
1,870.77
Say
1,870.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1549. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.