Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329
- Item number
- 18.72.4
- Analysis basis
- 10 metre
- Priced inputs
- 2
- Derived rate
- ₹2,880.70/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.4 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 250 mm dia Ductile Iron Class K-7 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹2,880.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 250mm dia. cast iron pipes (in 5.5 m
- lengths)
- Weight of 1 m pipes = 39.310 Kg
- Weight of 10m pipes 39.310x10 = 393.10
- Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7725 | MAT | Ductile Iron Class K7 pipe conforming to I.S. 8329 - 250mm diaDuctile Iron Class K- 7 pipe conforming to I.S. 8329 - 250 mm dia | metre | 10 | 1,925.00 | 19,250.00 |
| SUB | Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 3.93 | 361.65 | 1,421.28 |
- TOTAL
- 20,671.28
- Add 1 % Water charges on “W-A”
- +192.50
- TOTAL
- 20,863.78
- Add GST on “X-A” (multiplying factor 0.2127)
- +4,135.42
- TOTAL
- 24,999.20
- Add 15% CPOH on “Y-A”
- +3,536.69
- TOTAL
- 28,535.89
- Add Cess @ 1% on “Z-A”
- +271.15
- Cost of 10 metre
- 28,807.04
- Cost per metre
- 2,880.70
- SAY
- ₹2,880.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1536
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1536. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.