Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329

300 mm dia Ductile Iron Class K-9 pipes
Item number
18.72.19
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹4,344.40/ METRE
D-01/RATE ANALYSISITEM 18.72.19

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.19 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 300 mm dia Ductile Iron Class K-9 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹4,344.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 300mm dia. cast iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 60.490 Kg
  • Weight of 10m pipes 60.490x10 = 604.90
  • Kg
ANALYSIS OF RATES · ITEM 18.72.19DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7655MATDuctile Iron class K - 9 pipe Conforming to I.S. 8329 - 300mm diaDuctile Iron class K - 9 pipe Conforming to 1.S. 8329 - 300 mm diametre102,900.0029,000.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal6.049361.652,187.62
BUILD-UP TO RATE
TOTAL
31,187.62
Add 1 % Water charges on “W-A”
+290.00
TOTAL
31,477.62
Add GST on “X-A” (multiplying factor 0.2127)
+6,229.98
TOTAL
37,707.60
Add 15% CPOH on “Y-A”
+5,328.00
TOTAL
43,035.60
Add Cess @ 1% on “Z-A”
+408.48
Cost of 10 metre
43,444.08
Cost per metre
4,344.41
SAY
₹4,344.40
D-02/SOURCEPRINTED PAGE 1544
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1544

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1544. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.