Providing and laying S&S C.I. Standard specials such as tees, bends, collars tapers and caps etc, suitable for flanged jointing as per IS : 1538

Up to 300 mm dia
Item number
18.66.1
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹8,628.60/ QUINTAL
D-01/RATE ANALYSISITEM 18.66.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.66.1 (Providing and laying S&S C.I. Standard specials such as tees, bends, collars tapers and caps etc, suitable for flanged jointing as per IS : 1538 : Up to 300 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹8,628.60 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.66.1DETAILS OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7708MATS&S Centrifugally (Spun) C.I. Pipe Specials as per IS 1538 suitable for lead jointing upto 300mm diaS&S Centrifugally (Spun) C.I. Pipe Specials as per IS 1538 suitable for lead jointing up to 300 mm diaquintal15,600.005,600.00
SUBRate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24quintal1661.85661.85
BUILD-UP TO RATE
TOTAL
6,261.85
Add 1 % Water charges on “W-A”
+56.00
TOTAL
6,317.85
Add GST on “X-A” (multiplying factor 0.2127)
+1,203.03
TOTAL
7,520.88
Add 15% CPOH on “Y-A”
+1,028.85
TOTAL
8,549.73
Add Cess @ 1% on “Z-A”
+78.88
Cost of 1 quintal
8,628.61
SAY
₹8,628.60
D-02/SOURCEPRINTED PAGE 1519
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1519

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1519. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.