Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373
- Item number
- 18.61.1
- Analysis basis
- on no
- Priced inputs
- 4
- Derived rate
- ₹4,623.50/ DIRT BOX STAINER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.1 (Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 80 mm dia) is derived from 4 priced inputs for on no and works out to ₹4,623.50 per dirt box stainer after water charges, GST, CPOH and cess. The full build-up is below.
- Providing flanged joints to double acting
- air valves with bolts, nuts and rubber
- insertions etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7422 | MAT | Dirt box srainer 80 mmDirt box strainer 80 mm | each | 1 | 2,800.00 | 2,800.00 |
| 9977 | MAT | Carriage of dirt box strainer | L.S. | 26 | 2.27 | 59.02 |
| 9999 | MAT | Labour for laying dirt box strainer | L.S. | 39 | 2.27 | 88.53 |
| SUB | (Rate as per item no 18.30.1 of SH : Water Supply)Rate as per item 18.30.1 | each | 2 | 215.10 | 430.20 |
- TOTAL
- 3,377.75
- Add 1 % Water charges on “W-A”
- +29.48
- TOTAL
- 3,407.23
- Add GST on “X-A” (multiplying factor 0.2127)
- +633.21
- TOTAL
- 4,040.44
- Add 15% CPOH on “Y-A”
- +541.54
- TOTAL
- 4,581.98
- Add Cess @ 1% on “Z-A”
- +41.52
- Cost of 1 dirt box stainer
- 4,623.50
- SAY
- ₹4,623.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1515
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1515. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.