Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373

80 mm dia
Item number
18.61.1
Analysis basis
on no
Priced inputs
4
Derived rate
₹4,623.50/ DIRT BOX STAINER
D-01/RATE ANALYSISITEM 18.61.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.1 (Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 80 mm dia) is derived from 4 priced inputs for on no and works out to ₹4,623.50 per dirt box stainer after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Providing flanged joints to double acting
  • air valves with bolts, nuts and rubber
  • insertions etc.
ANALYSIS OF RATES · ITEM 18.61.1DETAILS OF COST FOR ON NO. DIRT BOX STRAINER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7422MATDirt box srainer 80 mmDirt box strainer 80 mmeach12,800.002,800.00
9977MATCarriage of dirt box strainerL.S.262.2759.02
9999MATLabour for laying dirt box strainerL.S.392.2788.53
SUB(Rate as per item no 18.30.1 of SH : Water Supply)Rate as per item 18.30.1each2215.10430.20
BUILD-UP TO RATE
TOTAL
3,377.75
Add 1 % Water charges on “W-A”
+29.48
TOTAL
3,407.23
Add GST on “X-A” (multiplying factor 0.2127)
+633.21
TOTAL
4,040.44
Add 15% CPOH on “Y-A”
+541.54
TOTAL
4,581.98
Add Cess @ 1% on “Z-A”
+41.52
Cost of 1 dirt box stainer
4,623.50
SAY
₹4,623.50
D-02/SOURCEPRINTED PAGE 1515
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1515

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1515. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.