CPWD Analysis of Rates · Water Supply
Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373
80 mm dia
- Item number
- 18.61.1
- Analysis basis
- Details of cost for on no. dirt box strainer
- Priced inputs
- 4
- Derived rate
- ₹4,623.50 / dirt box stainer
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.1 — Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 80 mm dia — is derived from 4 priced inputs for on no and works out to ₹4,623.50 per dirt box stainer after water charges, GST, CPOH and cess. The full build-up is below.
- Providing flanged joints to double acting
- air valves with bolts, nuts and rubber
- insertions etc.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7422 | Dirt box srainer 80 mmDirt box strainer 80 mmMaterial | each | 1 | 2,800.00 | 2,800.00 |
| 9977 | Carriage of dirt box strainerMaterial | L.S. | 26 | 2.27 | 59.02 |
| 9999 | Labour for laying dirt box strainerMaterial | L.S. | 39 | 2.27 | 88.53 |
| (Rate as per item no 18.30.1 of SH : Water Supply)Rate as per item 18.30.1Sub-analysis | each | 2 | 215.10 | 430.20 |
- TOTAL
- 3,377.75
- Add 1 % Water charges on “W-A”
- 29.48
- TOTAL
- 3,407.23
- Add GST on “X-A” (multiplying factor 0.2127)
- 633.21
- TOTAL
- 4,040.44
- Add 15% CPOH on “Y-A”
- 541.54
- TOTAL
- 4,581.98
- Add Cess @ 1% on “Z-A”
- 41.52
- Cost of 1 dirt box stainer
- 4,623.50
- Say
- 4,623.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1515. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.