CPWD Analysis of Rates · Water Supply
Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately)
150 mm dia nominal bore
- Item number
- 18.60.3
- Analysis basis
- Details of cost for one no. water meter
- Priced inputs
- 4
- Derived rate
- ₹8,408.80 / water meter
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.60.3 — Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately): 150 mm dia nominal bore — is derived from 4 priced inputs for one no and works out to ₹8,408.80 per water meter after water charges, GST, CPOH and cess. The full build-up is below.
- Providing flanged joints to double acting
- air valves with bolts, nuts and rubber
- insertions etc.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7420 | Water meter (including testing charges) 150 mmMaterial | each | 1 | 5,130.00 | 5,130.00 |
| 9977 | Carriage of water meterMaterial | L.S. | 39 | 2.27 | 88.53 |
| 9999 | Labour for laying water meterMaterial | L.S. | 65 | 2.27 | 147.55 |
| (Rate as per item No.18.30.4 Of SH: Water Supply)Rate as per item 18.30.4Sub-analysis | each | 2 | 387.40 | 774.80 |
- TOTAL
- 6,140.88
- Add 1 % Water charges on “W-A”
- 53.66
- TOTAL
- 6,194.54
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,152.78
- TOTAL
- 7,347.32
- Add 15% CPOH on “Y-A”
- 985.88
- TOTAL
- 8,333.20
- Add Cess @ 1% on “Z-A”
- 75.58
- Cost of 1 water meter
- 8,408.78
- Say
- 8,408.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1514. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.