Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately)
- Item number
- 18.60.3
- Analysis basis
- one no
- Priced inputs
- 4
- Derived rate
- ₹8,408.80/ WATER METER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.60.3 (Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately): 150 mm dia nominal bore) is derived from 4 priced inputs for one no and works out to ₹8,408.80 per water meter after water charges, GST, CPOH and cess. The full build-up is below.
- Providing flanged joints to double acting
- air valves with bolts, nuts and rubber
- insertions etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7420 | MAT | Water meter (including testing charges) 150 mm | each | 1 | 5,130.00 | 5,130.00 |
| 9977 | MAT | Carriage of water meter | L.S. | 39 | 2.27 | 88.53 |
| 9999 | MAT | Labour for laying water meter | L.S. | 65 | 2.27 | 147.55 |
| SUB | (Rate as per item No.18.30.4 Of SH: Water Supply)Rate as per item 18.30.4 | each | 2 | 387.40 | 774.80 |
- TOTAL
- 6,140.88
- Add 1 % Water charges on “W-A”
- +53.66
- TOTAL
- 6,194.54
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,152.78
- TOTAL
- 7,347.32
- Add 15% CPOH on “Y-A”
- +985.88
- TOTAL
- 8,333.20
- Add Cess @ 1% on “Z-A”
- +75.58
- Cost of 1 water meter
- 8,408.78
- SAY
- ₹8,408.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1514
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1514. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.