Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work

PN - 10 Pipe, 90 mm OD (SDR-11)
Item number
18.6.8
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹975.30/ METRE
D-01/RATE ANALYSISITEM 18.6.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.8 (Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 10 Pipe, 90 mm OD (SDR-11)) is derived from 5 priced inputs for 10 metre and works out to ₹975.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • LABOUR:
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.6.8DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8633MATPoly propyleneRandom - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 90 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 90 mm Outer diametre10386.003,860.00
0116LABFitter (grade 1)day0.37897.00331.89
0114LABBeldarday0.97736.00713.92
0114LABBeldarday0.8736.00588.80
0115LABBeldarCoolieday0.8736.00588.80
BUILD-UP TO RATE
Add 20% for fittings and wastage etc. on P, 20xP/100
+772.00
TOTAL
6,855.41
Add 1 % Water charges on “W”
+68.55
TOTAL
6,923.96
Add GST on “X” (multiplying factor 0.2127)
+1,472.73
TOTAL
8,396.69
Add 15% CPOH on “Y”
+1,259.50
TOTAL
9,656.19
Add Cess @ 1% on “Z”
+96.56
Cost of 10 metre
9,752.75
Cost of 1 metre
975.28
SAY
₹975.30
D-02/SOURCEPRINTED PAGE 1411
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1411

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1411. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.