CPWD Analysis of Rates · Water Supply

Providing and fixing C.I. double acting air valve of approved quality with bolts, nuts, rubber insertions etc. complete (The tail pieces, tapers etc if required will be paid separately)

80 mm dia

Item number
18.59.2
Analysis basis
Details of cost for 10 no. double acting air
Priced inputs
4
Derived rate
6,993.60 / air valve

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.59.2 Providing and fixing C.I. double acting air valve of approved quality with bolts, nuts, rubber insertions etc. complete (The tail pieces, tapers etc if required will be paid separately) : 80 mm dia — is derived from 4 priced inputs for 10 no and works out to ₹6,993.60 per air valve after water charges, GST, CPOH and cess. The full build-up is below.

  • valves
  • Providing flanged joints to double acting
  • air valves with bolts, nuts and rubber
  • insertions etc.
CodeInputUnitQuantityRate (INR)Amount (INR)
7416Double acting air valve 80 mmMaterialeach104,750.0047,500.00
9977Carriage of air valvesMaterialL.S.262.2759.02
9999Labour for laying double acting air valveMaterialL.S.392.2788.53
(Rate as per item no 18.30.1 of SH : Water Supply)Rate as per item 18.30.1Sub-analysiseach10215.102,151.00
TOTAL
49,798.55
Add 1 % Water charges on “W-A”
476.48
TOTAL
50,275.03
Add GST on “X-A” (multiplying factor 0.2127)
10,235.98
TOTAL
60,511.01
Add 15% CPOH on “Y-A”
8,754.00
TOTAL
69,265.01
Add Cess @ 1% on “Z-A”
671.14
Cost of 10 air valves
69,936.15
Cost of 1 air valve
6,993.62
Say
6,993.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1512. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.