Providing and fixing PTMT grating of approved quality and colour Rectangular type with openable circular lid
- Item number
- 18.58.2.1
- Analysis basis
- 1 no
- Priced inputs
- 2
- Derived rate
- ₹196.95/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.58.2.1 (Providing and fixing PTMT grating of approved quality and colour Rectangular type with openable circular lid 150 mm nominal size square 100 mm diameter of the inner hinged round grating) is derived from 2 priced inputs for 1 no and works out to ₹196.95 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7412 | MAT | Rectangular type with openable circular lid 150 mm size 18 mm high with 100 mm dia. (110 gm)Rectangular type with openable circular lid 150 mm size 18 mm high with 100 mm dia (110 gm) | each | 1 | 129.00 | 129.00 |
| 9988 | MAT | Carriage of materials and fixing charges | L.S. | 4.16 | 2.27 | 9.44 |
- TOTAL
- 138.44
- Add 1 % Water charges on “W”
- +1.38
- TOTAL
- 139.82
- Add GST on “X” (multiplying factor 0.2127)
- +29.74
- TOTAL
- 169.56
- Add 15% CPOH on “Y”
- +25.43
- TOTAL
- 194.99
- Add Cess @ 1% on “Z”
- +1.95
- Cost of 1 no.
- 196.94
- SAY
- ₹196.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1511
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1511. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.