Providing and fixing C.P. brass stop cock (concealed) of standard design and of approved make conforming to IS:8931
- Item number
- 18.52.1
- Analysis basis
- one no
- Priced inputs
- 2
- Derived rate
- ₹670.45/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.52.1 (Providing and fixing C.P. brass stop cock (concealed) of standard design and of approved make conforming to IS:8931 15 mm nominal bore) is derived from 2 priced inputs for one no and works out to ₹670.45 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7260 | MAT | C.P. Brass stop cock (concealed) 15 mm | each | 1 | 445.00 | 445.00 |
| 9988 | MAT | Carrige of material and fixing charges | L.S. | 11.57 | 2.27 | 26.26 |
- TOTAL
- 471.26
- Add 1 % Water charges on “W”
- +4.71
- TOTAL
- 475.97
- Add GST on “X” (multiplying factor 0.2127)
- +101.24
- TOTAL
- 577.21
- Add 15% CPOH on “Y”
- +86.58
- TOTAL
- 663.79
- Add Cess @ 1% on “Z”
- +6.64
- Cost of 1 no.
- 670.43
- SAY
- ₹670.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1505
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1505. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.