Skip to main content
R/DAR 2023

Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required

50 mm nominal bore
Item number
18.47.6
Analysis basis
one no
Priced inputs
4
Derived rate
₹1,520.80/ ONE NO
D-01/RATE ANALYSISITEM 18.47.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.47.6 (Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required: 50 mm nominal bore) is derived from 4 priced inputs for one no and works out to ₹1,520.80 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.47.6DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1646MATG.I. Union 50 mm nominal boreeach1330.00330.00
9988MATCarriage of materials and sundriesL.S.1.822.274.13
0116LABFitter (grade 1)day0.45897.00403.65
0114LABBeldarday0.45736.00331.20
BUILD-UP TO RATE
TOTAL
1,068.98
Add 1 % Water charges on “W”
+10.69
TOTAL
1,079.67
Add GST on “X” (multiplying factor 0.2127)
+229.65
TOTAL
1,309.32
Add 15% CPOH on “Y”
+196.40
TOTAL
1,505.72
Add Cess @ 1% on “Z”
+15.06
Cost for one no.
1,520.78
SAY
₹1,520.80
D-02/SOURCEPRINTED PAGE 1502
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1502

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1502. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.