Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required

32 mm nominal bore

Item number
18.47.4
Analysis basis
Details of cost for one no.
Priced inputs
4
Derived rate
1,000.15 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.47.4 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required: 32 mm nominal bore — is derived from 4 priced inputs for one no and works out to ₹1,000.15 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1644G.I. Union 32 mm nominal boreMaterialeach1160.00160.00
9988Carriage of materials and sundriesMaterialL.S.1.822.274.13
0116Fitter (grade 1)Labourday0.33897.00296.01
0114BeldarLabourday0.33736.00242.88
TOTAL
703.02
Add 1 % Water charges on “W”
7.03
TOTAL
710.05
Add GST on “X” (multiplying factor 0.2127)
151.03
TOTAL
861.08
Add 15% CPOH on “Y”
129.16
TOTAL
990.24
Add Cess @ 1% on “Z”
9.90
Cost for one no.
1,000.14
Say
1,000.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1501. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.