Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required

15 mm nominal bore

Item number
18.47.1
Analysis basis
Details of cost for one no.
Priced inputs
4
Derived rate
829.45 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.47.1 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required: 15 mm nominal bore — is derived from 4 priced inputs for one no and works out to ₹829.45 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1641G.I. Union 15 mm nominal boreMaterialeach140.0040.00
9988Carriage of materials and sundriesMaterialL.S.1.822.274.13
0116Fitter (grade 1)Labourday0.33897.00296.01
0114BeldarLabourday0.33736.00242.88
TOTAL
583.02
Add 1 % Water charges on “W”
5.83
TOTAL
588.85
Add GST on “X” (multiplying factor 0.2127)
125.25
TOTAL
714.10
Add 15% CPOH on “Y”
107.12
TOTAL
821.22
Add Cess @ 1% on “Z”
8.21
Cost for one no.
829.43
Say
829.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1500. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works