CPWD Analysis of Rates · Water Supply

Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making long screws etc. complete (New work)

40 mm nominal bore

Item number
18.46.5
Analysis basis
Details of cost for one no.
Priced inputs
4
Derived rate
631.30 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.46.5 Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making long screws etc. complete (New work): 40 mm nominal bore — is derived from 4 priced inputs for one no and works out to ₹631.30 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1645G.I. Union 40 mm nominal boreMaterialeach1260.00260.00
9988Carriage of materials and sundriesMaterialL.S.1.822.274.13
0116Fitter (grade 1)Labourday0.11897.0098.67
0114BeldarLabourday0.11736.0080.96
TOTAL
443.76
Add 1 % Water charges on “W”
4.44
TOTAL
448.20
Add GST on “X” (multiplying factor 0.2127)
95.33
TOTAL
543.53
Add 15% CPOH on “Y”
81.53
TOTAL
625.06
Add Cess @ 1% on “Z”
6.25
Cost for one no.
631.31
Say
631.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1499. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works