Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making long screws etc. complete (New work)
20 mm nominal bore
- Item number
- 18.46.2
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 4
- Derived rate
- ₹346.80 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.46.2 — Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making long screws etc. complete (New work): 20 mm nominal bore — is derived from 4 priced inputs for one no and works out to ₹346.80 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1642 | G.I. Union 20 mm nominal boreMaterial | each | 1 | 60.00 | 60.00 |
| 9988 | Carriage of materials and sundriesMaterial | L.S. | 1.82 | 2.27 | 4.13 |
| 0116 | Fitter (grade 1)Labour | day | 0.11 | 897.00 | 98.67 |
| 0114 | BeldarLabour | day | 0.11 | 736.00 | 80.96 |
- TOTAL
- 243.76
- Add 1 % Water charges on “W”
- 2.44
- TOTAL
- 246.20
- Add GST on “X” (multiplying factor 0.2127)
- 52.37
- TOTAL
- 298.57
- Add 15% CPOH on “Y”
- 44.79
- TOTAL
- 343.36
- Add Cess @ 1% on “Z”
- 3.43
- Cost for one no.
- 346.79
- Say
- 346.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1497. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.