CPWD Analysis of Rates · Water Supply
Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work
Sub analysis item for sand filling component
- Item number
- 18.41.1A
- Priced inputs
- 3
- Derived rate
- ₹2,087.30
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.41.1A — Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work : Sub analysis item for sand filling component — is derived from 3 priced inputs and works out to ₹2,087.30 after water charges, GST, CPOH and cess. The full build-up is below.
- Sub analysis item for sand filling
- component
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 6501 | Sand zone V (Jamuna)Material | cum | 1 | 1,320.00 | 1,320.00 |
| 0114 | BeldarLabour | day | 0.09 | 736.00 | 66.24 |
| 0115 | CoolieLabour | day | 0.11 | 736.00 | 80.96 |
- TOTAL
- 1,467.20
- Add 1 % Water charges on “W”
- 14.67
- TOTAL
- 1,481.87
- Add GST on “X” (multiplying factor 0.2127)
- 315.19
- TOTAL
- 1,797.06
- Add 15% CPOH on “Y”
- 269.56
- TOTAL
- 2,066.62
- Add Cess @ 1% on “Z”
- 20.67
- Cost of one cum.
- 2,087.29
- Say
- 2,087.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1490. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works