CPWD Analysis of Rates · Water Supply
Repainting G.I. pipes and fittings with synthetic enamel white paint with one coat of approved quality
50 mm diameter pipe
- Item number
- 18.39.6
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 2
- Derived rate
- ₹23.85 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.39.6 — Repainting G.I. pipes and fittings with synthetic enamel white paint with one coat of approved quality : 50 mm diameter pipe — is derived from 2 priced inputs for 10 metre and works out to ₹23.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Painting one coat with white paint on old
- work.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| (Rate as per item no 13.99.1 of S.H. Finishing)Rate as per item 13.99.1Sub-analysis | sqm | 1.894 | 102.80 | 194.70 | |
| 9999 | Add for delayMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 225.39
- Add 1 % Water charges on “W-A”
- 0.31
- TOTAL
- 225.70
- Add GST on “X-A” (multiplying factor 0.2127)
- 6.59
- TOTAL
- 232.29
- Add 15% CPOH on “Y-A”
- 5.64
- TOTAL
- 237.93
- Add Cess @ 1% on “Z-A”
- 0.43
- Cost of 10 metre
- 238.36
- Cost of one metre
- 23.84
- Say
- 23.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1486. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.