Providing flanged joints to double flanged C.I./ D.I. pipes and specials, including testing of joints
- Item number
- 18.30.2
- Analysis basis
- 10 joints
- Priced inputs
- 6
- Derived rate
- ₹332.00/ JOINTS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.30.2 (Providing flanged joints to double flanged C.I./ D.I. pipes and specials, including testing of joints : 100 mm diameter pipe) is derived from 6 priced inputs for 10 joints and works out to ₹332.00 per joints after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1374 | MAT | Rubber insertions for 100 mm dia pipe joints | each | 10 | 20.00 | 200.00 |
| 1956 | MAT | Bolts and nuts 16 mm dia 60 mm long | each | 80 | 12.00 | 960.00 |
| 9977 | MAT | Carriage of materials | L.S. | 4.16 | 2.27 | 9.44 |
| 0116 | LAB | Fitter (grade 1) | day | 0.25 | 897.00 | 224.25 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 0.25 | 816.00 | 204.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 2,333.69
- Add 1 % Water charges on “W”
- +23.34
- TOTAL
- 2,357.03
- Add GST on “X” (multiplying factor 0.2127)
- +501.34
- TOTAL
- 2,858.37
- Add 15% CPOH on “Y”
- +428.76
- TOTAL
- 3,287.13
- Add Cess @ 1% on “Z”
- +32.87
- Cost for 10 joints
- 3,320.00
- Cost for one joint
- 332.00
- SAY
- ₹332.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1461
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1461. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.