Skip to main content

CPWD Analysis of Rates · Water Supply

Supplying pig lead at site of work

Item number
18.29
Analysis basis
Details of cost for 1 quintal
Priced inputs
1
Derived rate
29,875.40 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.29 Supplying pig lead at site of work — is derived from 1 priced inputs for 1 quintal and works out to ₹29,875.40 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1397Pig leadMaterialkilogram100210.0021,000.00
TOTAL
21,000.00
Add 1 % Water charges on "W"
210.00
TOTAL
21,210.00
Add GST on "X" (multiplying factor 0.2127)
4,511.37
TOTAL
25,721.37
Add 15% CPOH on "Y"
3,858.21
TOTAL
29,579.58
Add Cess @ 1% on "Z"
295.80
Cost of one quintal
29,875.38
Say
29,875.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1461. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works