Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with clamps at 1.00 metre spacing. This includes the costs of cutting chases and including testing of joints complete as per direction of the engineer in charge. Concealed work, including cutting chases and making good the wall etc
- Item number
- 18.2.3
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹627.25/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.2.3 (Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with clamps at 1.00 metre spacing. This includes the costs of cutting chases and including testing of joints complete as per direction of the engineer in charge. Concealed work, including cutting chases and making good the wall etc 2025 (25 mm OD) pipe) is derived from 5 priced inputs for 10 metre and works out to ₹627.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 75 x P / 100
- Making chases upto 7.5 x 7.5 cm. in walls
- and making good the same
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8302 | MAT | 2025 mm PE-AL-PE Composit pressure pipe2025 mm PE-AL-PE Composite pressure pipe | metre | 10 | 95.00 | 950.00 |
| SUB | Rate as per item no. 18.78 of SH: Water SupplyRate as per item 18.78 | metre | 10 | 202.90 | 2,029.00 | |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 0.66 | 816.00 | 538.56 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
- Add 75% for fittings, clamps and wastage etc. on (P)
- +712.50
- TOTAL
- 5,011.83
- Add 1 % Water charges on “W-A”
- +29.83
- TOTAL
- 5,041.66
- Add GST on “X-A” (multiplying factor 0.2127)
- +640.79
- TOTAL
- 5,682.45
- Add 15% CPOH on “Y-A”
- +548.02
- TOTAL
- 6,230.47
- Add Cess @ 1% on “Z-A”
- +42.01
- Cost of 10 metre
- 6,272.48
- Cost of 1 metre
- 627.25
- SAY
- ₹627.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1399
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1399. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.