CPWD Analysis of Rates · Water Supply
Fixing water meter and stop cock in G.I. pipe line including cutting and threading the pipe and making long screws etc. complete (cost of water meter and stop cock to be paid separately)
- Item number
- 18.14
- Analysis basis
- Details of cost for one meter with stop cock
- Priced inputs
- 4
- Derived rate
- ₹812.30 / one meter
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.14 — Fixing water meter and stop cock in G.I. pipe line including cutting and threading the pipe and making long screws etc. complete (cost of water meter and stop cock to be paid separately) — is derived from 4 priced inputs for one meter and works out to ₹812.30 per one meter after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1555 | G.I. back (jam) nuts 25 mm diaMaterial | each | 1 | 20.00 | 20.00 |
| 9988 | Carriage of materials and sundriesMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| 0116 | Fitter (grade 1)Labour | day | 0.33 | 897.00 | 296.01 |
| 0114 | BeldarLabour | day | 0.33 | 736.00 | 242.88 |
- TOTAL
- 570.99
- Add 1 % Water charges on “W”
- 5.71
- TOTAL
- 576.70
- Add GST on “X” (multiplying factor 0.2127)
- 122.66
- TOTAL
- 699.36
- Add 15% CPOH on “Y”
- 104.90
- TOTAL
- 804.26
- Add Cess @ 1% on “Z”
- 8.04
- Cost of one meter with stop cock
- 812.30
- Say
- 812.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1435. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.