Fixing water meter and stop cock in G.I. pipe line including cutting and threading the pipe and making long screws etc. complete (cost of water meter and stop cock to be paid separately)
- Item number
- 18.14
- Analysis basis
- one meter
- Priced inputs
- 4
- Derived rate
- ₹812.30/ ONE METER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.14 (Fixing water meter and stop cock in G.I. pipe line including cutting and threading the pipe and making long screws etc. complete (cost of water meter and stop cock to be paid separately)) is derived from 4 priced inputs for one meter and works out to ₹812.30 per one meter after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1555 | MAT | G.I. back (jam) nuts 25 mm dia | each | 1 | 20.00 | 20.00 |
| 9988 | MAT | Carriage of materials and sundries | L.S. | 5.33 | 2.27 | 12.10 |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0114 | LAB | Beldar | day | 0.33 | 736.00 | 242.88 |
- TOTAL
- 570.99
- Add 1 % Water charges on “W”
- +5.71
- TOTAL
- 576.70
- Add GST on “X” (multiplying factor 0.2127)
- +122.66
- TOTAL
- 699.36
- Add 15% CPOH on “Y”
- +104.90
- TOTAL
- 804.26
- Add Cess @ 1% on “Z”
- +8.04
- Cost of one meter with stop cock
- 812.30
- SAY
- ₹812.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1435
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1435. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate