Making connection of G.I. distribution branch with G.I. main of following sizes by providing and fixing tee, including cutting and threading the pipe etc. complete
- Item number
- 18.13.1
- Analysis basis
- one connection
- Priced inputs
- 5
- Derived rate
- ₹911.90/ ONE CONNECTION
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.13.1 (Making connection of G.I. distribution branch with G.I. main of following sizes by providing and fixing tee, including cutting and threading the pipe etc. complete : 25 to 40 mm nominal bore) is derived from 5 priced inputs for one connection and works out to ₹911.90 per one connection after water charges, GST, CPOH and cess. The full build-up is below.
- Take 25mm dia as an average size.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1608 | MAT | G.I. tees (equal) 25 mm | each | 1 | 70.00 | 70.00 |
| 1555 | MAT | G.I. back (jam) nuts 25 mm dia | each | 1 | 20.00 | 20.00 |
| 9988 | MAT | Carriage of materials and sundries | L.S. | 5.33 | 2.27 | 12.10 |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0114 | LAB | Beldar | day | 0.33 | 736.00 | 242.88 |
- TOTAL
- 640.99
- Add 1 % Water charges on “W”
- +6.41
- TOTAL
- 647.40
- Add GST on “X” (multiplying factor 0.2127)
- +137.70
- TOTAL
- 785.10
- Add 15% CPOH on “Y”
- +117.77
- TOTAL
- 902.87
- Add Cess @ 1% on “Z”
- +9.03
- Cost of one connection
- 911.90
- SAY
- ₹911.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1435
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1435. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate