Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc. External work

65 mm dia nominal bore
Item number
18.12.7
Analysis basis
10 metre
Priced inputs
6
Derived rate
₹896.60/ METRE
D-01/RATE ANALYSISITEM 18.12.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.12.7 (Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc. External work 65 mm dia nominal bore) is derived from 6 priced inputs for 10 metre and works out to ₹896.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Weight for carriage = pipe weight + 2%
  • for fiitings = 1.02 * 66.30 = 68 kg = 0.068
  • tonne
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.12.7DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1551MATG.I. pipes 65 mm diametre10.2450.004,590.00
9999MATWhite lead, hemp, oil etc.L.S.13.522.2730.69
0116LABFitter (grade 1)day0.25897.00224.25
0114LABBeldarday0.66736.00485.76
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
TOTAL
6,302.22
Add 1 % Water charges on “W”
+63.02
TOTAL
6,365.24
Add GST on “X” (multiplying factor 0.2127)
+1,353.89
TOTAL
7,719.13
Add 15% CPOH on “Y”
+1,157.87
TOTAL
8,877.00
Add Cess @ 1% on “Z”
+88.77
Cost of 10 metre
8,965.77
Cost of 1 metre
896.58
SAY
₹896.60
D-02/SOURCEPRINTED PAGE 1433
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1433

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1433. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.